PMP® practice question: Execute with urgency to deliver value

Process domain · agile approach · easy

ProcessExecute with urgency to deliver valueeasy

A team using a kanban board has many items in progress but very few reaching completion, and cycle time is increasing. What is the most appropriate action?

  • AStart additional items so the team has work available if something becomes blocked.
  • BAssign each team member to a dedicated item to increase individual accountability.
  • CSet work-in-progress limits so the team finishes in-flight items before pulling new work.
  • DExtend the reporting period so cycle time appears more stable.

Explanation

Correct answer: C

Limiting work in progress improves flow and reduces cycle time; excess parallel work is what causes items to stall.

A
Starting more work is the cause of the problem, not the cure; it further fragments attention and lengthens cycle time.
B
Dedicating one item per person still leaves many items open simultaneously and ignores the need for swarming on blockers.
C
Correct. WIP limits force the team to finish before starting, which restores flow and brings cycle time down.
D
Changing the measurement window disguises the symptom without improving anything.