Several stakeholders complain that they are receiving either too much or too little project information, and not in a useful format. What should the project manager do?

  • ASend all stakeholders the same comprehensive weekly report.
  • BReduce all communications to a single monthly summary to limit complaints.
  • CReview and update the communications management plan to tailor the content, format, and frequency to each stakeholder's needs.
  • DDirect stakeholders to request information whenever they need it.

Explanation

Correct answer: C

Effective communication is planned and tailored to stakeholder needs.

A
A one-size-fits-all report is exactly the problem; different stakeholders need different information.
B
Cutting everyone back to a minimal summary trades one communication failure for another.
C
Correct. Tailoring communications via the plan matches the right information to each stakeholder.
D
A purely on-demand approach is reactive and likely to leave stakeholders under-informed.

Want to test yourself before seeing the answer? Answer questions interactively in practice mode — one at a time, with the explanation revealed only after you commit to a choice.