PMP® practice question: Integrate project planning activities

Process domain · predictive approach · easy

ProcessIntegrate project planning activitieseasy

A project manager is assigned to a new project but finds there is no clear statement of the project's objectives, high-level scope, or authority. What should the project manager do first?

  • AWork with the sponsor to develop the project charter that defines objectives, high-level scope, and the project manager's authority.
  • BBegin assigning tasks to the team to avoid losing time.
  • CCreate a detailed project schedule based on assumptions.
  • DWait for stakeholders to provide direction before taking any action.

Explanation

Correct answer: A

A project should be properly authorized; the charter establishes objectives, high-level scope, and authority.

A
Correct. Developing the charter with the sponsor formally authorizes the project and clarifies its purpose and the project manager's authority.
B
Assigning work before objectives and authority are clear risks effort in the wrong direction.
C
Detailed scheduling on unvalidated assumptions is premature without defined objectives.
D
Passive waiting stalls the project; the project manager should actively work with the sponsor to establish direction.