PM·PREP

PMP® practice question: Manage project changes

Process domain · predictive approach · easy

ProcessManage project changeseasy

On a predictive project, an influential stakeholder asks the project manager to add a significant new feature that was not in the approved scope. What should the project manager do?

  • AAdd the feature immediately to keep the stakeholder satisfied.
  • BDecline the request because it is outside the approved baseline.
  • CAsk the team to absorb the work without changing the schedule or budget.
  • DEvaluate the request through integrated change control, assessing its impact on scope, schedule, cost, and risk before a decision is made.

Explanation

Correct answer: D

Scope changes on predictive projects must go through integrated change control.

A
Adding scope without analysis or approval is uncontrolled change and undermines the baseline.
B
Refusing outright is also inappropriate; valid changes should be evaluated, not dismissed.
C
Absorbing unplanned work distorts the plan and sets an unsustainable precedent.
D
Correct. Assessing the impact and routing the request through change control lets the right authority decide with full information.

Want to test yourself before seeing the answer? Answer questions interactively in practice mode — one at a time, with the explanation revealed only after you commit to a choice.

More free Process questions

Browse all free questions →