PMP® practice question: Ensure knowledge transfer

Process domain · hybrid approach · easy

ProcessEnsure knowledge transfereasy

A project manager plans to hold a single lessons learned session at the end of a two-year project. A team member questions this approach. What is the better practice?

  • AKeep the single end-of-project session so that the full picture is available when lessons are captured.
  • BCapture lessons learned continuously throughout the project and apply them as the work proceeds.
  • CCapture lessons only when a significant problem occurs.
  • DDelegate lessons learned entirely to the PMO to record after closure.

Explanation

Correct answer: B

Knowledge is captured and applied throughout the project, benefiting the current project as well as future ones.

A
A single session at the end relies on two-year-old recollections and gives the current project no benefit at all.
B
Correct. Continuous capture preserves detail while it is fresh and allows the team to improve during the project rather than after it.
C
Recording only failures ignores the successful practices worth repeating and still delays capture.
D
The PMO may curate organizational knowledge, but capturing project lessons is the team's own responsibility during the work.