PMP® practice question: Manage project issues

Process domain · hybrid approach · easy

ProcessManage project issueseasy

A critical test environment has gone offline and the team cannot proceed with validation work today. How should the project manager treat this?

  • AAdd it to the risk register with a high probability rating.
  • BSubmit a change request to extend the schedule.
  • CRecord it in the assumption log for future reference.
  • DRecord it in the issue log with an owner and a target resolution date, and act to resolve it.

Explanation

Correct answer: D

A risk is an uncertain future event; once it has occurred, it is an issue and is tracked and resolved through the issue log.

A
The event is no longer uncertain, it has already happened, so it does not belong in the risk register.
B
A change request is premature; the impact is not yet known and the issue may be resolved the same day.
C
The assumption log records factors believed to be true for planning purposes, not events that have occurred.
D
Correct. An event that has occurred and is impeding progress is an issue, logged with an owner and resolution date so it can be actively driven to closure.

Want to test yourself before seeing the answer? Answer questions interactively in practice mode — one at a time, with the explanation revealed only after you commit to a choice.