PM·PREP

PMP® practice question: Evaluate and deliver project benefits and value

Business Environment domain · predictive approach · medium

Business EnvironmentEvaluate and deliver project benefits and valuemedium

Partway through a project, a shift in the market significantly weakens the business case that originally justified the project. What should the project manager do?

  • AContinue executing the project as planned, since it was already approved.
  • BAssess the impact of the change on the project's expected benefits and business value, and raise the findings with the sponsor and governance for a decision.
  • CCancel the project immediately to stop further spending.
  • DReduce the project's scope without consulting anyone to cut costs.

Explanation

Correct answer: B

The project manager keeps the project aligned with business value and escalates material threats to the business case appropriately.

A
Continuing without reassessment may waste resources on a project that no longer delivers sufficient value.
B
Correct. Evaluating the effect on benefits and bringing it to the sponsor and governance lets the right authority decide whether to continue, adjust, or stop.
C
Unilaterally canceling exceeds the project manager's authority and skips proper evaluation and governance.
D
Cutting scope without consultation is an uncoordinated decision that may not address the real issue and bypasses stakeholders.

Want to test yourself before seeing the answer? Answer questions interactively in practice mode — one at a time, with the explanation revealed only after you commit to a choice.

More free Business Environment questions

Browse all free questions →