World 02 · Level 7
Ambiguity
Process · L7
Q 1/100
ProcessPlan and manage budget
At a status point, a project reports planned value (PV) of 200,000 dollars, earned value (EV) of 170,000 dollars, and actual cost (AC) of 185,000 dollars. What do the schedule and cost variances indicate?
Keys: A–D or 1–4 to choose · ⌘/Ctrl+Enter to submit & advance