World 02 · Level 4
Under Pressure
Process · L4
Q 1/100
ProcessPlan and manage schedule
A project network has three paths from start to finish: Path 1 (A to B to C) totaling 14 days, Path 2 (A to D to E) totaling 18 days, and Path 3 (A to F to G) totaling 16 days. Activity F on Path 3 is delayed by 1 day. What is the effect on the project's completion date?
Keys: A–D or 1–4 to choose · ⌘/Ctrl+Enter to submit & advance