World 02 · Level 4

Under Pressure

ProcessPlan and manage schedule

A project network has three paths from start to finish: Path 1 (A to B to C) totaling 14 days, Path 2 (A to D to E) totaling 18 days, and Path 3 (A to F to G) totaling 16 days. Activity F on Path 3 is delayed by 1 day. What is the effect on the project's completion date?