ProcessExecute with urgency to deliver value
A public-agency project manager runs a hurricane-recovery housing-repair program. The team works repair packages strictly in the order applications were received, so minor porch repairs are proceeding while displaced families whose homes are uninhabitable have waited months. What should the project manager do?