ProcessAssess and manage risks

During buyout on a distribution-warehouse project, the roofing manufacturer tells the project manager that a regional plant changeover means an unusual discount and guaranteed early delivery if the roof membrane order is placed this month. Nothing like this appears in the risk register. What should the project manager do?