Business EnvironmentPlan and manage project compliance
During preconstruction on a hotel project, a mechanical trade contractor's project manager learns that the boiler plant cannot be placed into service until the state boiler inspector examines the pressure vessels and issues an operating certificate — an inspection only the state authority can perform and that the contractor cannot self-certify. How should the project manager handle this requirement?